Who this checklist is for
- Step 1: Confirm the exact battery pack before you request a quote
-
Step 2: Verify harness and accessory compatibility at the same time
-
Step 3: For imaging equipment, check the standard — not the vendor's quick-start guide
-
Step 4: Let the clinical side own what the clinical side owns
-
Step 5: Understand what the device is before you spec it
-
Step 6: Maintain the checklist itself
-
What goes wrong anyway
If you've just been handed the vendor list and the maintenance log, this is for you. Six steps. That's it. Not a philosophy of procurement — an actual sequence I run before I place an order or approve a repair. I built it after roughly nine years of doing this the sloppy way, and about $5,200 in wasted budget I'd rather not repeat.
Who this checklist is for
I coordinate equipment orders and maintenance scheduling across three sites — rehab, imaging, and surgical services. That means I'm the one who gets the email when a Permobil F5 won't hold a charge, when a radiography room cable tray doesn't fit, and when somebody wants to know why the oxygen concentrator in Bay 4 keeps alarming.
If your job looks anything like that — part purchasing, part troubleshooting, part translator between clinical staff and vendors — this maps reasonably well. If you're a solo clinic ordering one battery every three years, some of this is overkill. Honest warning.
What this doesn't cover: clinical decisions. I don't pick therapy settings, I don't approve imaging protocols, and I don't touch anything that carries a liability waiver. Step 4 covers that boundary in more detail.
Step 1: Confirm the exact battery pack before you request a quote
In my first year, I made the classic "standard means the same thing to everyone" error. Three mobility devices, one vendor, one purchase order. Cost me $1,140 straight to the trash plus a week of delay.
F5 battery replacement is the same trap, only more expensive. Electric wheelchairs do not share a universal battery. Voltage, capacity, pack enclosure, and — most importantly — the battery management system all differ. Order across a mixed fleet and you can hit different pack generations under the same model name.
What I confirm before any order goes out
- Photograph the nameplate. Do not copy a part number off an old invoice.
- Record the last six digits of the serial number alongside the pack part number.
- If the device has a connected diagnostic tool, have the tech read out the BMS firmware version.
- Get written confirmation (email is fine) that the part number applies to that serial range.
Sounds fussy. It is. But the alternative is what happened to us in September 2022: four battery packs at $640 each, dead on arrival because the pack wouldn't handshake with the controller. $2,560 gone, and four chairs out of service for eleven days.
One more thing people skip: replacement lithium packs ship as regulated goods. Ask for the UN 38.3 test summary up front. If a supplier can't produce it quickly, that's information.
Step 2: Verify harness and accessory compatibility at the same time
People check the main module and stop checking. Accessories are where it goes wrong, because accessories are usually specified by a different person in a different year.
When a dealer installs a Permobil backup camera, the camera isn't the problem. The problem is whether the camera talks to the display already on the chair, which connector type the camera uses, and where the harness actually routes. I lost roughly $430 on an 18-piece order where the cameras were fine, the displays were fine, and the connector was wrong. Optically perfect. Electrically useless.
Two questions I now ask before ordering, not after:
- "Can you send the harness diagram for this exact device configuration?"
- "Has this accessory had any return history for fitment mismatch?"
The second question makes some suppliers uncomfortable. Good. An uncomfortable supplier is usually a careful one.
Step 3: For imaging equipment, check the standard — not the vendor's quick-start guide
This is the step most people genuinely overlook. I've watched a new digital radiography room get inspected the week before go-live, and there's a specific reason that's a bad place to start.
Digital radiography systems sit under FDA performance standards for diagnostic X-ray systems and their major components (21 CFR 1020.30). That's not just a radiology concern. It means installation has defined thresholds, and not all of them are captured by a manufacturer's pre-installation checklist. If you're coordinating site readiness, read both, and read them early.
Three things I verify:
- Power quality. Get a voltage-drop test before you buy a line conditioner. Actually test it.
- Cable pathway. Confirm before the floor is finished. Not after. After costs you six weeks of coordination and a very unhappy facilities lead.
- Shielding and distances. This belongs to a medical physicist. Not me.
That last point matters more than it looks. I'm not a medical physicist, so I can't speak to shielding calculations. What I can do is sequence the construction work, the budget, and the vendor contacts so the physicist has what they need when they need it. If that sequencing fails, it isn't a technical failure. It's a scheduling failure with technical consequences.
Step 4: Let the clinical side own what the clinical side owns
A surgical robot is the clearest example. I'm the procurement person, not the engineer. I have no useful opinion on arm precision, sterile field setup, or how the cart moves through an OR. That's clinical and biomedical engineering territory.
My question is narrower and much duller: what does the service contract look like after we swap this in?
What I actually review, and what I hand off:
- Uptime SLA. What's written down, and what are the exclusions? Exclusions are where the money hides.
- Spare part availability. Ask where the parts live. "Central depot across the border" tells you a lot about your downtime risk.
- Training. Who, when, and is it bundled or billed separately?
Where I've gone wrong most often isn't price. It's spending three months negotiating price and then signing the service terms exactly as drafted. Twenty thousand saved on capital, then two outages in a year, and the math is gone.
Step 5: Understand what the device is before you spec it
So — what is an oxygen concentrator, practically speaking? Not a tank. It pulls in room air, passes it through a sieve bed that adsorbs nitrogen, and delivers concentrated oxygen continuously through tubing. No delivery schedule, no cylinder swaps, no storage room. It makes oxygen from ambient air, continuously, for as long as the power and the sieve beds hold up.
Once that clicks, the checklist questions change from "which one is cheapest" to:
- Fixed or portable? A portable unit on a shoulder strap and a portable unit with a wheeled case are very different daily experiences.
- How long can the tubing run? People forget this, then discover the unit doesn't reach the bed.
- Who owns the filters and sensors? Those are consumables, not repairs, and they frequently sit outside warranty.
To be fair, "maintenance-free" marketing exists because the routine parts are genuinely simple. But I'm somewhat skeptical of any supplier who won't say who replaces the sieve beds and when. That's either an oversight or a deliberate one.
Step 6: Maintain the checklist itself
This is the step people skip. Checklists rot. Vendors change policies, part numbers retire, firmware moves. An unmaintained checklist becomes a piece of paper that lives in a folder for two years and then gets used by somebody who trusts it.
I started maintaining ours after the third rejection from a long-standing supplier in Q1 2024. Third one. The first two I shrugged off. After that, we had a shared document with every rejection reason written into it, and a rule that nobody orders without a second set of eyes on the battery and harness lines.
Has it worked? In the past 18 months it's caught 47 potential errors before they became purchase orders. Some minor. Some were "we were about to buy the wrong pack again." It's tedious. Genuinely tedious. Still cheaper than the alternative.
What goes wrong anyway
Three caveats, then you're done.
- This worked for us, but we're a health system with predictable maintenance cycles and a stable vendor list. If you're dealing with donated equipment, mixed fleets, or seasonal demand, the sequencing will look different.
- The dollar figures above are our actual costs from 2016–2024, not current quotes. Verify pricing before you commit to anything.
- Nothing in here promises a device will never fail. Wheelchair packs degrade, X-ray tubes wear, concentrator sensors drift. That's aging, not incompetence.
And one hard rule: if a device is throwing a safety-relevant alarm — any brand, any category — it comes out of service and an authorized technician looks at it. No checklist substitutes for that.